1. A client is designing a system to support three 24x7 applications, each in a different environment. The plan is to host these applications on a new POWER7 based server to add to their existing POWER6 servers. Virtual I/O Server will not be used.
The applications have the following OS and processor requirements: AIX 6.1 with a peak of 2 cores between 10am-2pm
AIX 5.3 with a peak of 2 cores between 5pm-10pm
AIX 5.2 with a peak of 2 cores between 3am-7am
Outside the peak periods, the processor utilization is extremely low.
Which of the following configurations supports the design requirements?
A) A minimum of four processor activations is required.
Two dedicated processors for an AIX 5.2 LPAR.
AIX 5.3 and AIX 6.1 can share 2 processors
B) Each applications each needs its own LPAR running native AIX.
The LPAR must be running the appropriate version of AIX.
The LPARs can all use the shared pool and be uncapped.
C) The LPAR profiles can set the processor mode to POWER6
The AIX 6.1 and AIX 5.3 LPARs can be migrated using Live Partition Mobility.
The AIX 5.2 could only be migrated if it is in a WPAR.
D) The AIX 5.2 can be hosted in a WPAR in an AIX 7.1 LPAR.
The AIX 5.3 and AIX 6.1 can each have their own LPAR.
All LPARs can use the shared processor pool.
2. An administrator plans to implement Active Memory Expansion on several LPARs on a Power 770 system. Which tool should be used to determine the recommended LPAR settings for Active Memory Expansion?
A) amestat
B) amemon
C) amelpar
D) amepat
3. After installing a new VIO server partition an administrator noticed that the time zone is incorrectly set to CST6DST. The administrator would like the time zone set to Europe/London. Which command will achieve this?
A) chsys -timezone Europe/London
B) chzone -zone Europe/London
C) chtime -tz Europe/London
D) chdate -timezone Europe/London
4. An administrator must create several production and development LPARs on a new Power 770 server. Processor requirements for the development LPARs change frequently.
Which configuration will isolate the production LPARs from changes in processing requirements for the development LPARs?
A) Assign the development partitions to Shared Processor Pool 1 with the Maximum Pool
Capacity equal to the Entitled Pool Capacity.
Assign the production partitions to the default Shared Processor Pool 0.
B) Assign the production partitions to Shared Processor Pool 1 with the Maximum Pool
Capacity higher than the Entitled Pool Capacity.
Assign the development partitions to Shared Processor Pool 2 with the Maximum Pool
Capacity higher than the Entitled Pool Capacity.
C) Assign the production partitions to a Shared Processor Pool 2 with the Maximum Pool
Capacity equal to the Entitled Pool Capacity.
Assign the development partitions to the default Shared Processor Pool 1.
D) Assign the production partitions to Shared Processor Pool 1 with the Maximum Pool
Capacity equal to the Entitled Pool Capacity.
Assign the development partitions to Shared Processor Pool 2 with the Maximum Pool
Capacity equal to the Entitled Pool Capacity.
5. A redundant pair of VIO Servers is used to virtualize the same SAN LUNs to a number of AIX LPARs. To ensure that Multipath 10 is correctly configured an administrator sets the appropriate device attributes on the vSCSI disks on the clients.
One of the VIO Servers was shut down for 5 minutes to simulate a failure. After the VIO Server was brought back online, the administrator found that some LPARs recovered their storage paths automatically, yet some LPARs did not recover their paths at all.
How can the administrator recover from the lack of path recovery?
A) Update SDDPCM to a level higher than 2.1.2.3.
B) Allocate both vSCSI adapters to the client LPARs.
C) Reboot the client LPARs.
D) Reduce the number of paths to the LUNS to 6 or less.
질문과 대답:
| 질문 # 1 정답: D | 질문 # 2 정답: D | 질문 # 3 정답: D | 질문 # 4 정답: D | 질문 # 5 정답: C |














0 개 고객 리뷰
품질과 가치ITCertKR 의 높은 정확도를 보장하는 최고품질의 덤프는 IT인증시험에 대비하여 제작된것으로서 높은 적중율을 자랑하고 있습니다.
테스트 및 승인ITCertKR 의 덤프는 모두 엘리트한 전문가들이 실제시험문제를 분석하여 답을 작성한 만큼 시험문제의 적중률은 아주 높습니다.
쉽게 시험패스ITCertKR의 테스트 엔진을 사용하여 시험을 준비한다는것은 첫 번째 시도에서 인증시험 패스성공을 의미합니다.
주문하기전 체험ITCertKR의 각 제품은 무료 데모를 제공합니다. 구입하기로 결정하기 전에 덤프샘플문제로 덤프품질과 실용성을 검증할수 있습니다.